Malad City Councilwoman Resigns; Bannock Street Reconstruction Update
Malad City Councilwoman Jaime Olsen has announced her resignation from the Malad City Council as she prepares to move into a new home in Oneida County. Her final day of service is March 31.
Jaime was sworn in as a council member in January 2021. During her tenure, she was primarily assigned to Planning & Zoning and economic development, but she contributed in many other areas as well—often being the first to volunteer for additional responsibilities. She will be greatly missed.
Mayor Hawkins has conducted interviews with residents interested in filling the vacancy, and a new council member will be appointed soon.
Bannock Street Reconstruction Project
The remainder of this newsletter provides important information regarding the Bannock Street Reconstruction Project and how it will impact residents, commuters, and those accessing medical services.
The project has been awarded to Moreno & Nelson Construction Corp. of Eagle, Idaho, for $4,899,899. Forsgren Associates will serve as both the project engineer and construction inspector.
Funding for the project includes the following grants:
- STP Rural Grant (Phase I): $4.3 million for roadway reconstruction, sidewalks, curb and gutter, catch basins, and stormwater piping from 100 West to 300 West
- TAP Grant: $650,000 for sidewalks, curb and gutter, and stormwater piping from 300 West to the railroad tracks
- LSI Project: $1.96 million for road reconstruction from 300 West to 500 West
- FEMA Grant: $1 million for construction of a stormwater basin and piping to city property along Bush Avenue
Additionally, a $100,000 grant will fund an asphalt overlay from approximately the Oneida County Library to Bannock Street, which must be completed by September 30, 2026. The city will also replace a water pipeline between 100 West and 200 West as part of this project.
A second phase of the project (STP Rural Grant Phase II) has also been awarded, providing $2.2 million for improvements from the end of Phase I to 1100 West. Design is currently underway, with construction anticipated in 2029.
Construction Timeline and Impacts
Mobilization is currently underway. Residents may notice crews marking utilities, surveying, and bringing in heavy equipment.
Construction is expected to begin around April 1 at Malad City Park, focusing first on the stormwater drainage system. Work in this area is anticipated to be completed by May 22, ahead of the splash pad opening. While the park, walking path, and splash pad will remain open, visitors should exercise caution. Construction will occur along the north border of the park. The pickleball courts should remain accessible, though parking is recommended on the west end of Bush Avenue. At times, Bush Avenue may be temporarily closed. Depot Road may be used as an alternate route, though it will also undergo an overlay and serve as a truck detour.
A staging area will be located on city property south of the LDS Second/Fourth/Fifth Ward building on 100 West. Heavy equipment may also be present near the splash pad parking lot. Residents are urged to supervise children closely in these areas.
School, Traffic, and Access Information
It is planned that the major work on Bannock Street will not begin until after school is out so that children can continue to be dropped off at their regular bus stops. Sidewalks will remain in place until the end of the current school year to ensure safe pedestrian and student access. Some curbs may be removed earlier and will be clearly marked with caution tape.
Emergency vehicles and individuals accessing the Malad Valley Medical Clinic or Nell J. Redfield Memorial Hospital are encouraged to approach from the north rather than Bannock Street. Emergency access on Bannock Street will still be accommodated when necessary.
Residents will maintain access to their homes and driveways throughout construction; however:
- No curbside parking will be allowed on Bannock Street in the area of construction
- Temporary access interruptions may occur
- A 48-hour notice will be provided by the contractor if driveway access must be closed
- Sidewalk and driveway access will be limited during concrete work
Construction Schedule
Work hours will be Monday through Saturday, 7:00 a.m. to 6:00 p.m. Construction will pause on the following holidays:
- Memorial Day (May 25)
- Juneteenth (June 19)
- Independence Day (July 3–5)
- Labor Day (September 7)
- Columbus Day (October 12)
- Veterans Day (November 11)
Please note: the July 4 parade route will be modified due to construction.
Depot Road Work
Prior to major work on Bannock Street, an asphalt overlay will be completed on Depot Road to accommodate truck detours. This work is expected to begin in mid-April. Due to increased truck traffic, passenger vehicles may wish to avoid Depot Road during the construction period.
Thank You for Your Patience
We appreciate your patience and understanding as we complete this significant infrastructure project. The long-term benefits will outweigh the temporary inconvenience.
For questions or concerns, please contact:
- Tyler Webster, City Superintendent: 208-766-4160 (Ext. 3) or 816-344-4494
- You may meet in person with Mayor Hawkins and the engineer on most Tuesday afternoons, by making an appointment with the Malad City Clerk.